K & G Construction Co. v. Harris

Court of Appeals of Maryland · Decided October 24, 1960

Full citation

K & G Constr. Co. v. Harris, 164 A.2d 451 (Md. 1960).

Quote pages are pages of 223 Md. 305, the official report, so quotes and pinpoints cite it; for 164 A.2d 451, find the page in that reporter.

VerifiedQuotes, pinpoints and citation checked word for word against the opinion; facts checked against the opinion before publication. October 20, 2026.

K & G Construction Company

general contractorappellant

Harris et al.

subcontractorappellees

The parties: K & G Construction Company v. Harris et al..

Brief

Facts

K & G Construction Company owned a housing subdivision project and served as its general contractor. Harris and Brooks, the subcontractor, agreed to do the excavating and earth-moving work. The contract required the work to be done in "a workmanlike manner, and in accordance with the best practices." Time was of the essence, and the contractor was to make monthly progress payments by the 10th of the following month. On August 9, 1958, a bulldozer operator employed by the subcontractor drove too close to the contractor's house. A wall collapsed, and the damage was $3,400. The subcontractor and its insurer refused to pay or repair, claiming no liability. The contractor then refused to pay the subcontractor's July requisition, due August 10, 1958, because the house had not been repaired or paid for. The subcontractor kept working until September 12, 1958, then stopped and refused to return unless paid. Its unpaid completed work was worth $1,484.50. The parties stipulated that the subcontractor would have made a profit of $1,340.00 on the remaining work. They also stipulated that it cost the contractor $450 more than the contract price to have another contractor finish the job.

Issues

  1. Does a contractor, damaged by a subcontractor's failure to perform work in a workmanlike manner, have a right, under the circumstances of this case, to withhold an installment payment that was otherwise due under the contract?
  2. If the withholding was justified, did the subcontractor breach the contract by stopping work, so that it owed the contractor the added cost of finishing the job?

Holding

The promises to perform workmanlike work and to make monthly payments were mutually dependent. The subcontractor's negligent damage was a material breach, so the contractor could refuse the August 10 payment. The subcontractor's later stopping of work was itself a breach, making it liable for the $450 extra cost.

The rest of this brief is for subscribers

Every plan includes the procedural history, the rule and the reasoning, the IRAC and CREAC versions, every key quote with its pinpoint, the citation box with parallel citations and short forms and the exam angle.

Learn the citation form

Short video lessons on the rules behind this brief’s citations, each with two pause-and-practice exercises.

The Citation Code · citationcode.com/cases/k-and-g-construction-co-v-harris